Import Risks with Multiple Projects from PPM Risk

If you select a Risk Register with multiple projects, you will have to select one to associate with a PPM Risk project.

To import risks with multiple projects from PPM Risk, complete the following:

  1. Select the S3 // Risk tab.
  2. In the Import / Publish group, click PPM Risk.
  3. On the Connect PPM Risk Project dialog, navigate to the Select a Project field.
  4. Select a project from the dropdown menu.
  5. Navigate to the Select a PPM Risk Project field.
  6. Select a PPM Risk project.
  7. Click Link.
  8. In the Please Select Risks To Import dialog, select or clear the corresponding checkboxes of the risks you want to import.
  9. Click OK.
    After you have successfully linked a PPM Risk project to an Acumen project, an "E" icon will display next to the project name in the Risk Register tree.